Re: 55MW power plant: 240 T/hr or 75 T/hr steam?


[ Follow Ups ] [ Post Followup ] [ Boilerroom.com Steam-Forum - Number 4 ] [ FAQ ]

Posted by Boiler Guy on September 24, 2008 at 10:33:54:

In Reply to: 55MW power plant: 240 T/hr or 75 T/hr steam? posted by Dana L. Coe on September 24, 2008 at 10:25:18:

For starters what is the steam pressure, temperature, turbine type and eficiency, condensing assumed?

Boiler Guy

: I have a customer from India, wants to buy boilers for a 2 x 55MW electric plant. His calculations say they need 240 T/hr boilers, wear-as the Chinese boiler manufacturer swears 75 T/hr is fine.
: What gives? They both agree the price is about right, and the physical size, but somehow the tons of steam per hour is not the same.
: Anybody know what I'm missing here?