Re: Chemicals into FW line


[ Follow Ups ] [ Post Followup ] [ Boilerroom.com Steam-Forum - Number 3 ] [ FAQ ]

Posted by Kraig on September 25, 2004 at 14:21:17:

In Reply to: Chemicals into FW line posted by Chuck on April 23, 2004 at 17:09:16:

We are going through the same scenario, our chemical supplier wants the sulfite going into the DA and the volamine and polytreat going into the FW for each boiler.: What problems could one expect, if they used a system that injects chemicals (caustic, phosphate, sludge) into the feed water line that is supplying 3 boilers that operate at 200PSI?

: Most of the time 2 boilers are running, and the third is rotated in and out with the other two, so that at all times, at least to boilers are running. Load varies from 80 - 125Kpph.

: There is much more to this, but I am curious as to what you all think.

: Thanks,

: ~Chuck