[an error occurred while processing this directive]

Re: Shift Schedules


[ Follow Ups ] [ Post Followup ] [ Boilerroom.com Steam-Forum - Number 2 ] [ FAQ ]

Posted by tom on June 27, 2002 at 11:01:20:

In Reply to: Shift Schedules posted by michael painter on June 24, 2002 at 03:21:02:

At our plant operations work four operators. First shift works Wed-Sun with Mon and Tues off. Second shift works Thurs-Mon with Tues and Wed and off. Third shift works Sat-Wed with Thurs and Fri off. Relief works Mon day shift, Tues and Wed second, Thurs and Fri third. Tues is filled by a maintenance/relief engineer. Maintenance has two positions with 4 ten hour days, one Monday off, one Friday off. Other positions are standard five 8s. Weird setup maybe but has worked well for many, many years.