Re: sizing my boiler


[ Follow Ups ] [ Post Followup ] [ Boiler Room Residential and Home Forum #2 ] [ FAQ ]

Posted by HeatPro on September 17, 2004 at 09:15:33:

In Reply to: sizing my boiler posted by john on September 17, 2004 at 08:00:47:

The prudent allowance used by the IBR ratings method is to add 15% to the heat load to allow for piping and pickup allowances of a hot water system - so: 96,000 btuh output. Input would require knowing the efficiency of the unit, for instance:
at 85% efficiency another 1/7th is needed.